A refit loses least trade when decisions are made before work starts, materials with long lead times are ordered early, the paperwork is in place, and the work is sequenced so trades never wait on each other. Phasing the work or moving noisy tasks outside trading hours can keep part of the business open, within the limits set by the building and the community. We plan the sequence with you but do not promise fixed dates before the scope is clear.
Where does time really get lost on a refit?
Rarely in the work itself. Building tasks take the time they take, and an experienced team knows roughly how long. Time is lost in the gaps: waiting for a decision on a floor finish, a light fitting that arrives late, a specialist installer who is not ready when the ceiling is, a question to the town hall that nobody asked in advance, a change of mind after partitions are built.
That is why most of this guide is about preparation rather than speed. If the scope, the finishes and the paperwork are settled before the first wall comes down, the job runs as a sequence instead of a series of interruptions.
Which decisions should be closed before the start?
- Layout: final positions of counter, toilets, storage, staff area and any kitchen.
- Lighting plan: type and position of every fitting, because the ceiling is built around it.
- Finishes: floor, walls and colours, approved from samples.
- Specialists: who supplies shopfitting, air conditioning, security, signage and IT, and when they need access.
- Paperwork: what your technician has filed or applied for and what scope it covers.
- Working hours: what the building, the community and the landlord allow.
An open decision is not a disaster, but it should be visible. We list open points in the quote and show which stage of the work each one blocks.
How can a refit be phased so the shop stays open?
Phasing means dividing the unit into zones and completing one before starting the next. Customers use one part while the other is closed off with dust screens. It works best when the shop has a clear front and back, or separate areas such as a sales floor and a stockroom, and when the work in each zone can be finished without crossing into the other.
Phasing has costs: more set-up and clean-up, slower progress than an empty unit, and some disruption to customers. It rarely suits jobs where the whole floor or ceiling is replaced. We look at the layout with you and say honestly whether phasing makes sense or whether a short, well-planned closure is better.
Can noisy work be done outside trading hours?
Sometimes. Cutting, drilling and demolition can be grouped into early mornings, evenings or days when the shop is closed, leaving quieter tasks for opening hours. Whether that is possible depends on the building’s rules, the owners’ community, the neighbours above and around you, and local regulations on noise and working hours (to be verified for your address).
In residential buildings in particular, the community often sets limits. We agree working hours in writing before quoting, because they change both the plan and the cost. The guide on works and the owners’ community covers this side.
What should be ordered early?
Anything made to measure or imported tends to take longer than expected: shopfitting joinery, special light fittings, glazing, certain floor finishes, signage. The building work should not wait for these, and these should not arrive before the building is ready to receive them.
We draw up a simple list of items with long lead times at the start and agree who orders what. Where we purchase materials, we order them in line with the sequence; where you or your designer do, we tell you the latest date each item must be on site to avoid stopping the job. We do not give fixed delivery promises for products we do not control.
How do you keep a refit on schedule once it starts?
By keeping one plan, updated, and one person responsible for it. Each stage is checked before the next begins: services are tested before ceilings close, partitions are inspected before finishing, floors are protected before painting. Problems found on site — a pipe where it should not be, a wall out of plumb — are reported the same day with photos and a proposed solution, and nothing outside the quote proceeds without your approval.
You get a clear picture of where the job stands without having to chase anyone. That is the main difference between hiring one contractor and coordinating trades yourself.
How do you keep customers and staff safe if the shop stays open?
A shop that trades through a refit has to be safe first and attractive second. That means a physical separation between the work zone and the public, not just a strip of tape: screens that stop dust, a door or flap the team controls, and a route for customers that does not cross cables, tools or materials. Deliveries of materials and removal of debris are timed for moments when customer traffic is low, or routed through a back entrance where there is one.
Staff need to know which areas are off-limits and whom to ask if something looks wrong. Fire exits and escape routes must stay clear throughout. If those conditions cannot be met in your unit, closing for the noisy part of the job is the responsible choice, and we will say so.
What about the opening day itself?
Leave margin before an opening date that cannot move — a launch, a season, a lease clause. Furniture installation, stock delivery, IT set-up and staff training all need the unit after the builders have left, and the paperwork may need final checks. Our job ends with a clean unit and a walk-round to note any remaining details, which we close promptly.
For the practical side of the building work, see shop refurbishment and office refurbishment; for a broader view of what can go wrong, read red flags in a shop refit.
Official sources
- Ley 49/1960 on Horizontal Property, art. 7 (consolidated text published by sede.madrid.es)
- Ley 7/2021 (LISTA), arts. 137–138, as cited in a municipal declaración responsable form (Ayuntamiento de Vera)
Bauman Raymond Attila · Reforma Locales Málaga · Avenida Antonio Belón 3, Marbella. Last reviewed: 05/11/2026.